Construction Project of a Chinese Colliery

eep

 

System Integrator: EEP
Industry: Mining
Project(s): Colliery in China
Product: atvise® scada
PLCs UDP 200
Final Customer: China
atvise® Distributor: VIDEC Germany

videc

The tunnels of an underground coal mine have to be protected by spraying or filling the walls with construction material. Oven dry mixture is stored above ground in central bunkers and is pneumatically conveyed through pipes and points to various outlets in the underground. On site workers add water to the building material mixture and mix both with large agitator. This material is then injected by pumps on request, for example on wired mesh attached to the walls in order to secure the mountain.